- Water is still being pumped into SHD from Pump Station No 1. The telemetry still does not work but it is estimated is that is 45% full. It is important that the consultant who is being paid to run the telemetry actually makes an effort to get it working.
- The new submersible pump has arrived and just needs some electrics done before it will be in operation.
- Dedicated Pump and Pipeline from behand the weir to SHD has been ordered and being manufactured to be delivered within 15 working days and another 10 days to install.